Happycity Talegaon Varale Construction Updates August 2020
Updates on: 18th August, 2020
Work completed this month:
C Wing
12 slab in progress. External and Internal wall plaster, Plumbing, Tiling in progress. Brickwork completed till 8th floor, 9th floor in progress.
E Wing
10th Slab in progress.