Construction Update

Aikonic Phase 2 Construction Updates September 2020

Updates on: 23rd September, 2020

Work completed this month:

K Building - 2 BHK

RCC complete, Over Head water tank complete, Brick work complete, External plaster completed. Internal plaster, Dado tiles work etc internal work in progress

L Building - 1 BHK

RCC completed, Brick work in progress.