Happycity Talegaon Jijamata Chowk Construction Updates September 2020
Updates on: 23rd September, 2020
Work completed this month:
A Wing
Piling Completed.
B Wing
RCC work completed, Brickwork of 7th floor in progress.
C Wing
All slabs & brickwork done. External & Internal plaster completed.