Happycity Talegaon Varale Construction Updates November 2019
Updates on: 09th November, 2019
Work completed this month:
C Wing
8th Slab shuttering work in progress & 2nd floor brickwork in progress.
E Wing
Backfilling work in progress for Parking floor PCC work.