Eco City 2.0 Construction Updates December 2018
Updates on: 04th December, 2018
Work completed this month :
C1 -Building:
Ready for Possession
D1 - Building
Ready for Possession
C2 - Building
Flooring Work up to 10th Floor & 6th Internal work in progress, Lift work is in progress, Door fitting, internal ,External Painting & Internal work in progress
D2 - Building
External Painting work is in progress, Final Finishing work in Progress
D3 Building
7th slab is in progress
E1 - Building:
10th Slab is in progress, Electrical work in progress, Block work up to 6th floor completed
Infra Development work
Club House:Ready- we will handover soon for operational
Swimming Pool:Ready- we will handover soon for operational
Echoshoppy : Plinth Work Completed, 1st slab is in progress
Amenities Open Space 1 & Internal Road- in progress
Amenities Open Space 2 & Internal Road- in progress