Work completed this month :
A - Building:
17th Slab Completed, Brick Work - 17 floors completed, Internal Gypsum - 15TH Floor Completed, Tiling - kitchen otta 14th Floor completed, OVERHEAD WATER TANK - WORK IN PROGRESS, External Plaster - 65% Completed
B - Building:
17th slab completed, Brick Work - 15 Floors completed, OVERHEAD WATER TANK COMPLETED, Internal gypsum - 14th floor completed, EXTERNAL PLASTER - West Side Completed, South Side Completed, East Side Completed, North side 60% Completed, Toilet, kitchen and dry balcony dado work - Upto 7th Floor, Kitchen Platform - 15th Floor Completed, Flooring - 1st Floor Completed
C - Building:
Piling work Completed, Footing - Completed
Infra Development
Club House - Ready
Swimming pool with Baby Pool - Ready
Amphitheatre - Ready
Deck Area - Ready
Barbeque Area - Ready
Gazebo - Ready
Basket Ball court - Ready
Multi purpose Court - Ready
Children's Play Area - Ready
Skating Area - Ready
Walking Track - Ready
Services
Water tank RCC Work completed
STP CIVIL WORK Completed
Podium Work in Progress