Life 360 Degree Construction Updates May 2019

Life 360 Degree Construction Updates May 2019

Work completed this month :

A – Building:

17th Slab Completed, Brick Work – 17 floors completed, Internal Gypsum – 13TH Floor Completed, Tiling – kitchen otta 10th Floor completed, Dado tiles – Upto 3rd floor, OVERHEAD WATER TANK – WORK IN PROGRESS, External Plaster – 40% Completed

B – Building:

17th slab completed, Brick Work – 15 Floors completed, OVERHEAD WATER TANK COMPLETED, Internal gypsum – 14th floor completed, EXTERNAL PLASTER – West Side completed, South Side – completed, East Side – Completed, North side – 60% Completed, Toilet, kitchen and dry balcony dado work – Upto 6th Floor, Kitchen Platform – 15th Floor Completed

C – Building:

Piling work Completed, Pile Cap Work – 40% Completed

Infra Development

Club House – Ready

Swimming pool with Baby Pool – Ready

Amphitheatre – Ready

Deck Area – Ready

Barbeque Area – Ready

Gazebo – Ready

Basket Ball court – Ready

Multi purpose Court – Ready

Children’s Play Area – Ready

Skating Area – Ready

Walking Track – Ready

 