Work completed this month :

A – Building:

17th Slab Completed, Brick Work – 17 floors completed, Internal Gypsum – 15TH Floor Completed, Tiling – kitchen otta 14th Floor completed, OVERHEAD WATER TANK – WORK IN PROGRESS, External Plaster – 65% Completed

B – Building:

17th slab completed, Brick Work – 15 Floors completed, OVERHEAD WATER TANK COMPLETED, Internal gypsum – 14th floor completed, EXTERNAL PLASTER – West Side Completed, South Side Completed, East Side Completed, North side 60% Completed, Toilet, kitchen and dry balcony dado work – Upto 7th Floor, Kitchen Platform – 15th Floor Completed, Flooring – 1st Floor Completed

C – Building:

Piling work Completed, Footing – Completed

Infra Development

Club House – Ready

Swimming pool with Baby Pool – Ready

Amphitheatre – Ready

Deck Area – Ready

Barbeque Area – Ready

Gazebo – Ready

Basket Ball court – Ready

Multi purpose Court – Ready

Children’s Play Area – Ready

Skating Area – Ready

Walking Track – Ready

Services

Water tank RCC Work completed
STP CIVIL WORK Completed
Podium Work in Progress

 