Ecocity Construction Updates September 2018

Ecocity Construction Updates September 2018

Work completed this month :

C1 -Building:

Ready for Possession

D1 – Building

Ready for Possession

C2 – Building

RCC Work Completed, Internal work in progress, Flooring Work up to 3rd Floor

D2 – Building

Internal work in progress, Flooring Work up to 9th Floor

D3 Building

3rd slab is in progress

E1 – Building

9th Slab in progress

Infra Development work

Club House: Ready

Swimming Pool: Ready

Echoshoppy :Footing work Completed, Plinth Work in progress

 

 