Ecocity Construction Updates June 2018

Ecocity Construction Updates June 2018

Work completed this month :

C1 -Building:

Final Finishing  work is in progress

D1 – Building

Ready for Possession

C2 – Building

11th Slab is in progress

D2 – Building

12th Slab in progress

D3 Building

1st Slab in progress

E1 – Building

7th Slab in Progress

Infra Development work

Club House: Final Finishing work is in progress

Swimming Pool: Waterproofing work completed, Tiling work in progress

Entrance Gate: Completed

UG Water Tank: Waterproofing completed, Pump Room work done

C1 & D1:

  • Strom water & Electrical line work completed
  • Lift Ready for use
  • Internal RCC road work is Completed

STP Tank: RCC work completed, waterproofing work done.
MSEB TRANSFORMER: Work is completed
 D1 WATER CONNECTION:  Done
C1 WATER CONNECTION: Done