Eco City 2.0 Construction Updates December 2018

Eco City 2.0 Construction Updates December 2018

Work completed this month :

C1 -Building:

Ready for Possession

D1 – Building

Ready for Possession

C2 – Building

Flooring Work up to 10th Floor & 6th Internal work in progress, Lift work is in progress,Door fitting ,

internal ,External Painting &  Internal work in progress

D2 – Building

External Painting work is in progress, Final Finishing work in Progress

D3 Building

7th slab is in progress

E1 – Building:

10th Slab is in progress, Electrical work in progress, Block work up to 6th floor completed

Infra Development work

Club House:Ready- we will handover soon for operational

Swimming Pool:Ready- we will handover soon for operational

Echoshoppy : Plinth Work Completed, 1st slab is in progress

Amenities Open Space 1 & Internal Road-  in progress

Amenities Open Space 2 & Internal Road-  in progress

 