Ecocity Construction Updates December 2017

Ecocity Construction Updates December 2017

Work completed this month :

C1 – Building
  • 12th Slab Completed.
  • Flooring ( Tiles) work is in progress up to 6th floor.
  • Electrical basic work up to 12th floor.
  • Concealed Plumbing working in progress up to 10th Floor.
  • Bathroom & Toilet Dado Tiles work in progress up to 6th Floor.
  • Kitchen Platform & Stone Work 8th Floor.
  • Waterproofing working on the 10th floor.
  • Parapet wall is in progress.
D1 – Building
  • 12th Slab completed.
  • Flooring ( Tiles) work in progress up to 12th floor.
  • Electrical basic work up to 12th floor.
  • Concealed Plumbing working in progress up to 12th Floor.
  • Bathroom & Toilet Dado Tiles work in progress up to 12th Floor.
  • Kitchen Platform & Stone Work up to 12th Floor.
  • Waterproofing working up to 12th floor completed.
  • Overhead Water tank work in progress.
  • Internal wall Putty works up to the 9th floor.
  • Gypsum works up to 4th Floor.
  • Balcony Railing work up to 10th Floor.
C2 – Building
  • 1st Slab Completed.
  • Mivan Shuttering & steelwork is in progress.
  • 2nd Slab is in progress.
D2 – Building
  • Mivan Shuttering & steel work completed.
  • 4th Slab is in progress.
D3 Building
  • Excavation work completed.
  • PCC work is done.
  • Footing work is in progress.
E1 – Building
  • Plinth work is Completed.
  • 1st Slab Colmoun work is completed.
  • 1st Slab casting is in progress.

Infra Development work

  • Club House- RCC work Completed
  • Brick Work completed
  • Plastering work is in progress
  • Electrical,plumbing,tilling work is in progress
  • Entrance Gate- 2nd Slab completed
  • UG Water Tank -waterproofing is in progress
  • Drainage Line – C1 & D1 bldg completed
  • STP Tank – RCC work is in progress

 