Eco City 2.0 Construction Updates February 2019

Eco City 2.0 Construction Updates February 2019

Work completed this month :

C1 -Building:

Ready for Possession

D1 – Building

Ready for Possession

C2 – Building

RCC Work Completed, Lift work in progress , Door fitting , External ,Internal Painting &  Internal work in progress

D2 – Building

Ready for Possession

D3 Building

10th slab is Completed & Internal work started

E1 – Building:

10th Slab Completed, Electrical & External Plastering work in progress , Block work up to 10th floor is in progress

Infra Development work

Club House & Swimming Pool  :Ready

Amenities Open Space 1 –  in progress

Amenities Open Space 2 –  in progress

 