AIKONIC SITE UPDATE PHOTOGRAPHS AUGUST 2018

AIKONIC SITE UPDATE PHOTOGRAPHS AUGUST 2018

Work completed this month :

  • A & B – Wing: ¬†FLOORING DONE , INTERNAL PAINT OF EVERY FLAT WORK IN PROCESS EXTERNAL PAINT & LIFT INSTALLATION WORK IN PROCESS.
  • C – Wing: FLOORING DONE , EXTERNAL PAINT & LIFT INSTALLATION WORK IN PROCESS.
  • D, E & F – Wing : FLOORING DONE , EXTERNAL PAINT & LIFT INSTALLATION WORK IN PROCESS.
  • G, H, I –¬†Wings: FINAL SLAB COMPLETED , BRICK WORK STARTED OF ALL WING.

 