Construction Update

Shrinagari III Talegaon Dabhade, Pune Construction Updates June 2021

Updates on: 09th June, 2021
Building A - RCC work, brickwork, external & internal plaster completed.  Internal gypsum work, granite work in progress.


Building B - RCC work, brickwork, internal plaster Completed.  External plaster, window granite frame, internal plumbing in progress.