Construction Update

Eco City 2.0 Construction Updates May 2019

Updates on: 28th May, 2019

Work completed this month :

C1 - Building

Ready for Possession

D1 - Building

Ready for Possession

C2 - Building

Ready for Possession

D2 - Building

Ready for Possession

D3 - Building

RCC work Completed, Flooring work Completed, Electrical, Plumbing, wall putty, Door fitting work in progress, External Painting work in progress

E1 - Building

10th Slab Completed, Electrical, Internal & External Plastering work in progress, Kitchen Platform & Plumbing work in progress

Ecoshoppy

3rd Slab in progress

Infra Development work

Club House & Swimming Pool - Ready
Amenities Open Space 1 - In Progress
Amenities Open Space 2 - In Progress