Eco City 2.0 Construction Updates February 2019
Updates on: 08th February, 2019
Work completed this month :
C1 -Building:
Ready for Possession
D1 - Building
Ready for Possession
C2 - Building
RCC Work Completed, Lift work in progress , Door fitting , External ,Internal Painting & Internal work in progress
D2 - Building
Ready for Possession
D3 Building
10th slab is Completed & Internal work started
E1 - Building:
10th Slab Completed, Electrical & External Plastering work in progress , Block work up to 10th floor is in progress
Infra Development work
Club House & Swimming Pool: Ready
Amenities Open Space 1 - in progress
Amenities Open Space 2 - in progress