Construction Update

Eco City 2.0 Construction Updates February 2019

Updates on: 08th February, 2019

Work completed this month :

C1 -Building:
Ready for Possession
D1 - Building
Ready for Possession
C2 - Building
RCC Work Completed, Lift work in progress , Door fitting , External ,Internal Painting &  Internal work in progress
D2 - Building
Ready for Possession
D3 Building
10th slab is Completed & Internal work started
E1 - Building:
10th Slab Completed, Electrical & External Plastering work in progress , Block work up to 10th floor is in progress

Infra Development work

Club House & Swimming Pool: Ready
Amenities Open Space 1 -  in progress
Amenities Open Space 2 -  in progress