Building wise work status as below:
Building K - RCC work, Brickwork, External & Internal Plaster completed, Tiling, Door Frame, Window Frame Completed, Lift & electrical work Completed, Building Outer paint structure work in progress.
Building L - RCC work, Brickwork done. External & Internal plaster Completed, Tiling, Lift work completed. Door Frame & Window Frame working in progress, Building Outer paint structure work in progress.
Infra Development works in progress.
Aikonic Phase I (J Building) - All slab work completed. Brickwork and Building overhead water tank work in progress.