Construction Update

Aikonic Phase 2 Talegaon Dabhade, Pune Construction Updates June 2021

Updates on: 07th June, 2021

Building wise work status as below:


Building K - RCC work, Brickwork, External & Internal Plaster completed, Tiling,  Door Frame, Window Frame Completed, Lift & electrical work Completed, Building Outer paint structure work in progress.


Building L - RCC work, Brickwork done. External & Internal plaster Completed, Tiling, Lift work completed.  Door Frame & Window Frame working in progress,  Building Outer paint structure work in progress.


Infra Development works in progress.


Aikonic Phase I (J Building) - All slab work completed. Brickwork and Building overhead water tank work in progress.