Building wise work status as below
Building K - RCC work, Brickwork, External & Internal Plaster completed, Tiling, Door Frame, Window Frame Completed, Lift & electrical work Completed, Building Outer paint structure work Completed. cp sanitary fitting work in progress
Building L - RCC work, Brickwork done. External & Internal plaster Completed, Tiling, Lift work completed. Door Frame & Window Framework Completed, Building Outer paint structure work in progress & cp sanitary fitting work in progress
Infra Development works in progress.
Aikonic Phase I ( J Building ) - RCC work, Brickwork is done. External & Internal plaster Completed, Tiling, Lift work in progress. Door Frame & Window Framework in progress, Building Outer paint structure work in progress