Aikonic Phase 2 Construction Updates March 2021
Updates on: 26th March, 2021
Work completed this month:
K Building
RCC work, Brickwork, External & Internal Plaster completed, Tiling Completed, Door Frame, Lift & Window Frame working in progress.
L Building
RCC work, Brickwork done. External & Internal plaster Completed, Tiling work completed. Door Frame, Lift & Window Frame working in progress.
Infra Development work in progress.