Aikonic Phase 2 Construction Updates March 2021

Updates on: 26th March, 2021

Work completed this month:

K Building

RCC work, Brickwork, External & Internal Plaster completed, Tiling Completed, Door Frame, Lift & Window Frame working in progress.

L Building

RCC work, Brickwork done. External & Internal plaster Completed, Tiling work completed. Door Frame, Lift & Window Frame working in progress.

Infra Development work in progress.