RCC Construction Ready till 12 floors
Blick work done till 9 floors
Kitchen Internal plaster,
Dry balcony and bathroom internal plasters done till 6th floors
Electrical boxes Work of Kitchen, Dry Balcony, all bathrooms ready till 9th floor.
Electricals points of the entire unit ready till 3rd Floor