Ecocity Construction Updates November 2017

Ecocity Construction Updates November 2017

Work Status :

  • C1 BLDG
    • 12th Slab is in progress
    • Flooring ( Tiles) work is in progress up to 4th floor
    • Electrical basic work up to 11th floor
    • Concealed Plumbing working in progress up to 8th Floor
    • Bathroom & Toilet Dado Tiles work in progress up to 5th Floor
    • Kitchen Platform & Stone Work 7th Floor
    • Waterproofing working on 5th floor
  • C2 BLDG
    • 1st Slab Completed.
  • D1 BLDG
    • 12th Slab completed
    • Flooring ( Tiles) work in progress up to 11th floor
    • Electrical basic work up to 12th floor
    • Concealed Plumbing working in progress up to 12th Floor
    • Bathroom & Toilet Dado Tiles work in progress up to 12th Floor
    • Kitchen Platform & Stone Work up to 11th Floor
    • Waterproofing working up to 12th floor & Top Terrace
    • Overhead Water tank work in progress
    • Internal wall Putty work up to 7th floor
    • Balcony Railing work up to 7th Floor
  • D2 BLDG
    • Mivan Shuttering & steel work completed
    • 2nd Slab is in progress.
  • D3 BLDG
    • Excavation work completed
    • Footing work is in progress
  • E1 BLDG
    • Plinth work is Completed.
    • 1st Slab Colmoun work is completed
    • 1st Slab casting is in progress
  • Infra Development work
    • Club House Plinth work Completed & 2nd Slab completed
    • Ground floor Brick work is completed
    • Swimming Pool Excavation work done
    • Entrance Gate work Footing & Plinth work Completed
    • Column work in progress
    • UG Water Tank work in progress
    • C1 & D1 Drainage line work is completed
    • STP Tank work is in progress

 