Ecocity Construction Updates March 2018

Ecocity Construction Updates March 2018

Work completed this month :

C1 -Building:

RCC work Completed, Internal work is in progress

D1 – Building

RCC work Completed, Internal work is in progress.

C2 – Building

6th Slab is in progress

D2 – Building

8th Slab is in progress

D3 Building

Plinth work is in progress

E1 – Building

4th Slab is in progress

Infra Development work

Club House-

  • Internal work is in progress
  • Tiling work completed
  • Electrical, plumbing, tilling work done

Swimming Pool: Waterproofing work completed, UG Tank completed

Entrance Gate: RCC & Plastering work completed

UG Water Tank: Waterproofing completed, Pump Room work done

C1 & D1:

  • Strom water & Electrical line work completed
  • Lift setup work completed, Elevators work in progress
  • Internal RCC road work in progress

STP Tank: RCC work completed, waterproofing work done