Ecocity Construction Updates December 2018

Ecocity Construction Updates December 2018

Work completed this month :

C1 – Building

RCC work Completed, Internal work is in progress –

  • Flooring ( Tiles) work is in progress up to 8th floor.
  • Concealed Plumbing working in progress up to 11th Floor.
  • Bathroom & Toilet Dado Tiles work in progress up to 8th Floor.
  • Kitchen Platform & Stone Work 10th Floor.
  • Bathroom & Toilet Dado Tiles work in progress up to 6th Floor.
  • Waterproofing working on 10th floor
  • External texture painting is in progress
  • Door Framework is in progress
  • Overhead Water tank work in progress
D1 – Building

RCC work Completed, Internal work is in progress –

  • Flooring ( Tiles) work in progress up to 12th floor.
  • Electrical basic work up to 12th floor.
  • Concealed Plumbing working in progress to 12th Floor.
  • Bathroom & Toilet Dado Tiles work in progress up to 12th Floor.
  • Kitchen Platform & Stone Work up to 12th Floor.
  • Waterproofing working is done.
  • Overhead Water tank work in progress.
  • Internal wall Putti work up to the 10th floor.
  • Gypsum plastering works up to 6th Floor.
  • Balcony Railing work completed.
  • External texture painting is in progress.
  • Door Framework is in progress.
C2 – Building
  • 3rd Slab is in progress
D2 – Building
  • 5th Slab is in progress
D3 Building
  • Footing & Plinth work is in progress
E1 – Building
  • 2nd Slab is in progress

Infra Development work

Club House-

  • Internal work is in progress.
  • Tiling work is in progress.
  • Electrical, plumbing, tilling work is in progress.
  • Entrance Gate- RCC work completed.
  • UG Water Tank -waterproofing completed.
  • C1 & D1-Strom water & Electrical line work completed.
  • C1 & D1- Lift setup work is in progress.
  • STP Tank – RCC work is in progress.

 