Ecocity Construction Updates September 2017

Ecocity Construction Updates September 2017

Work completed this month :

  • D1 BLDG .– 12th Slab Completed
  • C2 BLDG. – 1st Slab Completed.
  • D2 BLDG. – 1st Slab Completed.

Work in progress :

  • C1 BLDG. – 9th Slab is in progress
  • E1 BLDG. – Plinth work is in Progress.
  • D3 BLDG. – Footing work is in Progress.

 